Affected Areas (Building #) |
Power-out Date |
Museumof Art(MOA,151) |
07:00~ 10:00 (3h) |
Institute of Environmental |
07:00~ 20:00(13h) |
Office of Admissions(150) | |
CJ InternationalCenter(152) |
○ Construction Details
- Installation of transformer in building #150: replacement of the existing one(250KVA) with a new one(600KVA)
- Replacement of gauges: protective devices and relays replacement
- Wiring work: power line extension for transformer installation
- Inspection before power restoration: by Korea Electrical Safety Corporation (KESC)
○ Notes
- To minimize discomfort, please notify all students, faculties, and staffs about the power-out
in advance.
- To prevent damage to electrical appliances, unplug them all appliancesprior to the power outage.
- Once electricity returns, proceed with caution before using electrical appliances.
- The actual power outage duration may differ from the stated schedule depending on operational
circumstances.